Preparing cost of goods sold budget


Question:

Preparing cost of goods sold budget

Prepare a cost of goods sold budget for the Summit Manufacturing Company for the year ended December 31, 2011, from the following estimates. Inventories of production units:

 

Work in

Finished

 

Process

Goods

1-Jan-11

$28,500

$19,300

December 31, 2011

23,700

22,400

Direct materials purchased during the year, $854,000; beginning inventory of direct materials, $31,000; and ending inventory of direct materials, $26,000. Totals from other budgets included:

Direct labor cost

$539,500

Total factory overhead costs

818,000