Assignment:
The home office billing department of a chain of department stores prepares monthly inventory reports for use by the stores' purchasing agents. Given the following information, use the critical path method to answer the questions below.
JOB AND DESCRIPTION |
IMMEDIATE PREDECESSORS |
TIME (HOURS) |
a |
Start |
- |
0 |
b |
Get computer printouts of customer purchases |
a |
10 |
c |
Get stock records for the month |
a |
20 |
d |
Reconcile purchase printouts and stock records |
b, c |
30 |
e |
Total stock records by department |
b, c |
20 |
f |
Determine reorder quantities for coming period |
e |
40 |
g |
Prepare stock reports for purchasing agents |
d, f |
20 |
h |
Finish |
g |
0 |
|
a. How long will the total process take? (Number of hours)
b. Which jobs can be delayed without delaying the early start of any subsequent activity?