Prepare work breakdown structure explaining task durations


The HR department at the iTech company offers a job position to Kim Jones. She will start the new job after three weeks. As an IT department member, you were asked to set up an orientation for her, including meeting with human resources, users, and the IT team. Tour at the company needs also to be organized. You suggested the following schedule: First, Kim have to meet with the human resources to learn about the company benefits and policies (3 hours). After finishing the meeting, she has to handle three tasks at once: she could tour the company offices (4 hours), meet with the users (3 hours), and work on the necessary paperwork (2 hours). Then, after meeting the IT manager and with all the paperwork completed, she would meet with the entire IT team for a brief introduction (1 hours).

Tasks:

1. Prepare a work breakdown structure explaining task, durations, and predecessor task.

2. Calculate the start and finish date for each task and determine the critical path.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Prepare work breakdown structure explaining task durations
Reference No:- TGS02940224

Expected delivery within 24 Hours