Question: You are the Senior Project manager on a $50 million, high visibility project for a major insurance company. The project has been moving along with few issues - the performing organization has been doing an outstanding job. You have been asked to prepare a report for senior management showing the progress of the team. The best report to be used under these circumstances would be: Milestone report. Critical Path analysis. Gantt chart. Variance report.