Question: For a hardware manufacturer, prepare graphs and analyze the internal failure costs for the past 6 months using the net sales index.

Month                     Cost                   Net sales (thousands)

Mar                      $45,300                       $755

Apr                       $45,800                       $790

May                       $46,100                       $840

June                      $47,000                       $925

July                        $48,600                    $1,050

Aug                        $49,300                    $1,232