Prepare an MRP for scissors. Lead times are one day for each component and final scissor assembly, but two days for the plastic grips. 634 pairs of scissors are needed on Day 6. Note: There are 200 straight blades and 350 bent blades on hand, and 31 top blade assemblies on hand.