Prepare an eup schedule


Problem:

(Cost assignment; WA) CushionRide manufactures automobile springs. Its production equipment is fairly old, and one bad unit is typically produced for every 20 good units. The bad units cannot be reworked and must be discarded. Spoilage is determined at an end-of-process inspection point. CushionRide uses a weighted average process costing system and adds all material at the beginning of the process. The following data have been gathered from the accounting records for January 2001:

Beginning inventory (60% complete as to conversion)

4,000 units

Units started

20,000 units

Ending inventory (30% complete as to conversion)

3,000 units

Good units completed

20,000 units


Material

Conversion

Total

Beginning inventory

$ 12,492

$ 9,927

$ 22,419

Current period

112,548

63,000

175,548

Total costs

$125,040

$72,927

$197,967

a. Prepare an EUP schedule.

b. Determine the cost of the normal spoilage and allocate that cost to the appropriate inventory.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Prepare an eup schedule
Reference No:- TGS02038309

Expected delivery within 24 Hours