Prepare a network diagram for activities using microsoft


The activities involved in a computer installation project are given below:

Description

Activity

Preceding Activity

 (Days)

Physical preparation

A

-

4

Organisational planning

B

A

2

Personal selection

C

A

36

Equipment installation

D

B

15

Personnel training

E

D

4

Detailed system designing

F

E

9

File conversion

G

F

9

Establishment of standards

H

C

2

Program preparation

I

B

10

Program testing

J

D

9

Finishing Documentation

K

G,H,I,J

20

Follow Up

L

K

20

Required:

i. Prepare a network diagram for activities using Microsoft Project.

ii. Calculate the Project Duration.

iii. Clearly mark the Critical Path.