Prepare a master schedule like that shown in Figure 11.11 given this information: The forecast for each week of an eight-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows:
Week
|
Customer Orders
|
1
|
52
|
2
|
35
|
3
|
20
|
4
|
12
|
Use a production lot size of 75 units and no beginning inventory.