Prepare a job cost estimate for a customer


Questions:

Frames Ltd produces wooden window frames to order for the building industry. The size of frame depends on the specification in the contract. For the purposes of providing job cost estimates the size of frame is ignored and the job cost estimate is based on the type of frame produced, being either single-glazing or double-glazing. The standard specification is as follows:

 

 

Single-glazing

£

Double-glazing

£

Direct materials per unit

90.00

130.00

Direct labour per unit

 

 

6.5 hours at £5.00 per hour

32.50

 

8.0 hours at £5.00 per hour

 

40.00

Variable production overhead charged at £6 per hour

39.00

48.00

 

 

 

 

Fixed overhead is estimated at £160,000 per month for single-glazing and £100,000 per month for double-glazing. Estimated production per month for single-glazing is 4,000 units and for double-glazing is 2,000 units per month.

Required

Prepare a job cost estimate for a customer who intends to order 500 single-glazed and 200 double-glazed units.