Preparation of gantt chart and network diagram for


The planning department of an electronics firm has set up the activities for developing and producing a new CD Player. Given the information below, develop a project network using Microsoft Project. Assume a five-day workweek and the project starts on January 6, 2014. 

Activity ID

Description

Activity Predecessor

Activity Time (Weeks)

1

Staff

None

2

2

Develop Market Program

1

3

3

Select Channels of Distribution

1

8

4

Patent

1

12

5

Pilot Production

1

4

6

Test Market

5

4

7

Ad Promotion

2

4

8

Set up for Production

4, 6

16

The project team has requested that you create a network for the project and determine if the project can be completed in 45 weeks.

Additional Requirement

This assignment belongs to Operations Management and it is a case study where a Gantt Chart and network diagram wants to be ready. For this purpose MS Project has been used.

Word Limit 300