Willis expected its annual overhead costs to be $300,000 and direct labor costs to be $500,000. Actual overhead was $290,000, and actual labor costs totaled $550,000. How much is the company's predetermined overhead rate to the nearest cent?
a. $0.58
b. $0.53
c. $0.55
d. $0.60