1.Define predecessor, successor, and parallel activities. Give a real world example of each. 
Predecessor activities - those activities that must be completed before another activity can be started. Ex: Computer's OS must be installed before loading an application package.
 
 Successor activities - activities that must follow a particular activity in some type of sequence. Ex: a program must be tested and then documented after it is compiled.
 
 Parallel activities - an activity or task that can be worked at the same time as another activity. Ex: Design web page layouts and set-up server 
2. In the context of critical chain project management, what is resource contention?  
3.Define the following and give a real world example of each (other than the ones described in the text book): Finish-to-Start; Start-to-Start; Finish-to-Finish; Start-to-Finish.  
4.     Assume the following activities for a project along with their estimated durations and predecessors. Describe how critical path analysis would be applied to this project, and calculate the critical path. Define the concepts: slack/float, expedite/crash, and fast tracking and explain what their implications are for this project?  
Hint: Start with the following steps:
a.       Draw AON diagram
b.       Calculate Possible Activity paths
c.       Identify critical path
 
|  | Estimated Duration in Days | Predecessor | 
| A | 2 | None | 
| B | 4 | A | 
| C | 3 | A | 
| D | 1 | C,B | 
| E | 1 | C,D | 
| F | 3 | D,E | 
| G | 2 | F | 
Critical Path: A-B-G-F-H
 Slack/Float: amount of time an activity can be delayed before it delays the project Expedite/Crash: adding resources to an activity on the critical path to shorten duration Fast Tracking: completing activities in parallel to shorten critical path 
5.     What are the seven IT project risk management processes?  
6.     What is a risk response plan? What should be included? 
7.     Compare the three types of project risk: known, known-unknown, and unknown-unknown. Give an example (not discussed in the text book) of each. 
8.      Describe the qualities of a good project metric.  
9.       Given the following information, is the Project in trouble?
Calculate: 
a.       Cost Variance (CV) : (CV) = EV − AC
b.      Schedule Variance (SV):  (SV) = EV − PV
c.       Cost Performance Index  (CPI) : (CPI) = EV/AC
d.      Schedule Performance Index (SPI):  (SPI) = EV/PV 
10.  What are the key differences (4-5) between the Agile Project Management approach and Waterfall (Traditional Project Management) 
11.  What was your favorite topic in this course?