Polar containers make high-end coolers for camping. The total task time needed to make a cooler is 360 seconds, with the longest individual task taking 50 seconds. Polar containers would like to set up a line capable of producing 50 coolers per 8-hour day. What is the task time? What is the maximum output per day? (hint: consider the longest individual task time.) show work