Planned order release
When should planned order release(s) take place for the material requirements planning (MRP) data shown below? (use the matrix as a work sheet) Quantity = 60; Lead Time = 3 weeks
Period (week) 1 2 3 4 5
Requirements 80 -- 90 -- 90
Scheduled Receipts 60
Projected Stock balance 190
Planned Order Release
A - Week 1
B - Week 2
C - Week 3
D - Week 4