Using the Pert Mustang Case Study
1. Assume 45 working days are available to to completed the project including transporting the car to Detroit before the auto show begins. Your report should briefly discuss the aspects of the proposed new business such as the competitive priorities that Roberts asked about
2. Construct a table containing the project activities using the letter assigned to each activity the time estimates, and the precedence relationships from which you will assemble the network diagram.
3. Draw a network diagram of the project determine the activities on the critical path and the estimated slack for each activity.
4. Prepare a project budget showing the cost of each activity and the total for the project. Can the project be completed with the budget? Will the project require more than $3,600 in any week? To answer this question assume the activities B, C, and D must be paid for when the item is received (the earliest finish time for the activity). Assume that the costs of all other activities that span more than one week can be prorated. Each week contains five work days. If problems exist, how might Roberts overcome them?