Question - Perry Company gathered the following actual results for the current month:
Actual amounts:
Units produced 5,500
Direct labor cost (1 0,000 hours) $53,000
Budgeted production and standard costs were:
Budgeted production 4,600
Direct labor 4 hrs/unit at $9.50!hr.
Required - What is the direct labor efficiency variance?