Perform the analysis for the engineer at 15 per


A pipeline engineer working in Kuwait for the oil giant BP wants to perform a present worth analysis on alternative pipeline routings-the first predominately by land and the second primarily undersea. The undersea route is more expensive initially due to extra corrosion protection and installation costs, but cheaper security and maintenance reduces annual costs. Perform the analysis for the engineer at 15% per year.


Land

Undersea

Installation cost, $ million

215

350

Pumping, operating, security,

22

2

$ million per year



Replacement of valves and

30

70

appurtenances in year 25, $ million



Expected life, years

50

50