Overhead project costs indirect costs are 70 per day


Time-Cost Trade-Offs

Activity

Predecessor

Total Normal time (day)

Total Crash time (day)

Total Normal cost ($)

Total Crash cost ($)

Available crashing days

Crashing cost per day       (cost slope)

A

---

6

5

60

90

 

 

B

---

7

4

50

150

 

 

C

A

6

4

100

200

 

 

D

A

7

7

30

30

 

 

E

B

5

4

70

85

 

 

F

C

9

7

40

120

 

 

G

E, D

7

4

50

230

 

 

Overhead project costs  (Indirect costs) are $70 per day.

Please crash the project and find the project schedule with the lowest total cost (indirect cost + direct cost).

Rule of thumb:

Crash the project one period at a time.

Crash the least expensive activity that is on the critical path.

Critical path will very likely change after each crashing, find new critical path each time before crashing.