Austin Company manufactures 2 products, Flacca and Gordo. Overhead costs are comprised of machine set-ups $1,600,000; machining $3,600,000; and inspecting $1,200,000. Recent data are shown below:
Flacca Gordo
Direct labor hours 15,000 25,000
Machine setups 600 400
Machine hours 24,000 26,000
Inspections 800 700
Overhead assigned to Flacca using a single overhead rate based on direct labor hours and using ABC, respectively, would be: