Optimal sequence for jobs to be scheduled


Assignment:

The following set of seven jobs is to be processed through two work centers at George Heinrich’s printing company. The sequence is first printing, then binding. Processing time at each of the work centers is shown in the following table:

Job Printing (Hours) Binding (Hours)
T 15 3
U 7 9
V 4 10
W 7 6
X 10 9
Y 4 5
Z 7 8

a) What is the optimal sequence for these jobs to be scheduled?
b) Chart these jobs through the two work centers.
c) What is the total length of time of this optimal solution?
d) What is the idle time in the binding shop, given the optimal solution?
e) How much would the binding machine’s idle time be cut by splitting Job Z in half.

Provide complete and step by step solution for the question and show calculations and use formulas.

Request for Solution File

Ask an Expert for Answer!!
Supply Chain Management: Optimal sequence for jobs to be scheduled
Reference No:- TGS01954793

Expected delivery within 24 Hours