Given the following information
Activity Duration (in days)
1-2 8
1-3 4
2-4 6
2-5 11
3-5 9
4-5 3
5-6 5
Required
a) Draw the network
b) Calculate the earliest and latest time
c) What is the critical path
d) What is the critical time