Operation Management, MRP, Material Resource Planning
In a material requirements plan (MRP) the order release date is calculated by:
a - adding ordering lead time to the project date of material shortage
b - determining project date of material shortage by backing up by the order lead time period.
c - adding the ordering lead time to the finished goods delivery date called for in the master scheduled
d - adding demand during lead time to safety stock
I believe the answer is B not completely sure