Operating cash flow-level of output


A project has a contribution margin of $5, projected fixed costs of $12,000, a projected variable cost per unit of $12, and a projected present value break-even point of 5,000 units. What is the operating cash flow at this level of output?

A. $1,000

B. $12,000

C. $13,000

D. $68,000

E. $73,000

Solution Preview :

Prepared by a verified Expert
Finance Basics: Operating cash flow-level of output
Reference No:- TGS0680342

Now Priced at $5 (50% Discount)

Recommended (90%)