Operating an mrp system


Question 1: Which kind of MRP system is employed as an information system to plan and control the inventories and capacities?

A. Type I   
B. Type II   
C. ERP   
D. None of above

Question 2: Which of the given is not a manner of handling uncertainty when operating an MRP system?

A. Safety stock   
B. Safety lead time   
C. Safety capacity   
D. Back-up suppliers

Question 3: _______ system employs requirements order philosophy, while _____ system uses the replenishment order philosophy.

A. Order point, MRP   
B. MRP, order point   
C. EOQ, Quantity Discount   
D. P, Q   
E. Q, P

Question 4: The next two questions refer to the given table that defines a project.

1764_defining a table.jpg

The minimum time needed to complete the project is:

A. 37 days   
B. 24 days   
C. 22 days   
D. 21 days   
E. none of the above

Question 5: By using the data of Question above, the slack time for activity B is:

A. 0 day   
B. 1 day   
C. 3 days   
D. 7 days   