One difference between the project manager and contract manager is:
A) Content knowledge resides mainly with the contract manager, and knowledge of legal contacting ramifications typically resides with the project administrator.
B) the project manager handles the entire procurement process, while the contract administrator only comes in at the end of the project during contract closure
C) content knowledge resides mainly with the project manager, and knowledge of legal contracting ramifications typically resides with the contract administrator
D) the contract manager is involved in all aspects of the procurement process, but the project manager is only there to draft to the scope of work.