One common way to compute the estimate to completion (ETC) is to add the budget at completion (BAC) and the value already earned, and
If AC = 900, PV = 800, SPI = 0.90, and the project was supposed to be 40% done by now, what is the current EAC assuming performance will not change for the rest of the project?