On the schedule of cost of goods manufactured which


1. On the schedule of cost of goods manufactured:

a. beginning work-in-process plus direct materials used equals manufacturing costs.

b. cost of goods manufactured is the same thing as total manufacturing costs.

c. work-in-process will necessarily increase if total manufacturing costs increase.

d. factory overhead plus beginning work-in-process equals manufacturing costs.

e. None of these.

2. Which costing method seems ideally suited to the production of homogenous products in continuous throughput?

a. Activity-based costing.

b. Job order costing.

c. Process costing.

d. Absorption costing.

e. None of these.

3. Frick Company uses a job order cost system and applies overhead based on estimated rates. The overhead application rate is based on total estimated overhead costs of $200,000 and direct labor hours of 50,000. For job 836, direct labor hours were 800.

a. Factory Overhead should be debited for $3,200.

b. Factory Overhead should be credited for $3,200.

c. Overhead Expense should be debited for $3,200.

d. Overhead Expense should be credited for $3,200.

e. None of these.

4. For job 1838, there were 1,000 direct labor hours, and actual overhead was $500 for depreciation and $1,400 for indirect labor. Overhead is applied at $2 per direct labor hour. Which account should be debited for $1,900?

a. Work in Process.

b. Cost of Goods Sold.

c. Factory Overhead.

d. Cost of Goods Manufactured.

e. None of these.

Request for Solution File

Ask an Expert for Answer!!
Financial Accounting: On the schedule of cost of goods manufactured which
Reference No:- TGS01050451

Expected delivery within 24 Hours