on june 15 2011 sanderson construction entered


On June 15, 2011, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.C. for $215 million. The expected completion date is April 1 of 2013, just in time for the 2013 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):


2011
2012 2013
Costs incurred during the year $ 40
$ 80
$ 50
Estimated costs to complete as of 12/31
120

60

-

Determine the amount of gross profit or loss to be recognized in each of the three years using the percentage-of-completion method.