Question - On January 4th, Stevens Manufacturing received an order for 30 uniforms. The following information pertained to that order.
Hours Required
Receive and process order-0.25
Waiting for production to begin-1.25
Cutting-50.00
Sewing and lettering-300.00
Moving materials from one station to another-20.00
Waiting for an operation to begin-95.00
Packaging35.00Loading to be shipped-0.50
In transit to customer-5.00
Calculate the manufacturing cycle efficiency.
10%
69%
70%
60%