On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows:

  January 1, 2016

$330,000

  September 1, 2016

$495,000

  December 31, 2016

$495,000

  March 31, 2017

$495,000

  September 30, 2017

$330,000

Dreamworld had $6,500,000 in 12% bonds outstanding through both years.
Dreamworld's capitalized interest in 2016 was:
$39,600.
$79,200.
$59,400.
$69,300. 

 