On a shovel/truck operation the production of the shovel is 293 BCY/h and a job efficiency of 0.75. The trucks used have a capacity of 12 BCY and have a cycle time of 45 min.(excluding loading).
a) How many trucks are required and what is the production of the system.
b) If you lose one truck for a day, what will be the production that day.