Olin Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1382 per unit; variable costs = $263 per unit; fixed costs = $3925292; quantity = 70721 units. Suppose the company believes all of its estimates are accurate only within +/-19 percent.
What is the company's EBIT when it performs its best-case scenario analysis?