Problem: For the next six months, Brett Company projects the following information (in units).
Jan Feb Mar April May June
Retail demand 200 200 300 300 400 400
Dealer demand 400 500 600 700 800 900
Shop capacity 1,000 1,000 1,000 1,000 1,000 1,000
Painting capacity 700 700 700 1,200 1,200 1,200
Demand drives production for that month and cannot be carried over from one month to another. Retail customers are satisfied first.
The number of dealer units that will be produced and sold in March is:
a. a. 400 units
b. b. 600 units
c. c. 700 units
d. d. 1000 units