Normal distribution of project completion


A project has completion time of 24 weeks with the variance of 9 weeks. Supposing that the project completion time follows the normal distribution, evaluate the following:

a) The probability that project will be finished in less than 20 weeks.

b) The probability that project will be finished in more than 26 weeks.

c) The probability that project will be finished between 20 weeks and 26 weeks.

Request for Solution File

Ask an Expert for Answer!!
Project Management: Normal distribution of project completion
Reference No:- TGS014309

Expected delivery within 24 Hours