Normal critical path-crash critical path


Assignment:

Activity    Normal time    Crash time    Normal cost    Crash cost
1-2    3    2    1000    1500
2-3    4    2    2000    4000
2-4    4    3    2500    3500
3-5    3    1    1500    2500
4-5    4    2    6000    12000
5-6    6    3    2000    5000

Determine:

a) Normal critical path.

b) Crash critical path.

c) The first and last activities to be crashed.

d) Minimum project completion time with the least increase in the cost over normal costs.

e) The minimum completion time, assuming a budget of $23,500.

f) The minimum cost to complete the project in 12 weeks.