Non-value-added cost per unit


In addition, the current profit per unit must be maintained.

Information about the product (for production of 4,000) is as follows.

Standard Quantity Actual Quantity Actual Cost

Materials (pounds) 5,800 6,000 $60,000
Labor (hours) 1,800 2,000 $20,000
Setups (hours) 0 225 $8,000
Material handling (moves) 0 400 $5,000
Warranties (number repaired) 0 300 $15,000

Required:

a) Calculate the target cost for maintaining current market share and profitability.

b) Calculate the non-value-added cost per unit.

c) If non-value-added costs can be reduced to zero, can the target cost be achieved?

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Non-value-added cost per unit
Reference No:- TGS038334

Expected delivery within 24 Hours