New communication system for commercial planes


Question: The R&D dept. is planning to bid on a large project for the development of a new communication system for commercial planes.  The accompanying table shows the activities, time & sequence required:

Activity    Immediate predecessor    Time (weeks)

A                           ---                          3
B                            A                           2
C                            A                           4
D                            A                           4
E                            B                            6
F                           C,D                          6
G                           D,F                          2
H                            D                            3
I                           E,G,H                        3

Q1. What is the critical path?

Q2. Suppose you want to shorten the completion time as much as possible, & you have the option of shortening any or all of B,C,D, and G each one week. Which would you shorten?

Q3. What is the new critical path & earliest completion time? (from b’s answer  I think)

Please solve using Microsoft Excel & show any work if possible.  Thanks!

Solution Preview :

Prepared by a verified Expert
Other Management: New communication system for commercial planes
Reference No:- TGS01447324

Now Priced at $20 (50% Discount)

Recommended (92%)

Rated (4.4/5)