Problem: The R&D dept. is planning to bid on the large project for development of the new communication system for commercial planes. The accompanying table demonstrate the activities, time & sequence required:

Question1. Sketch the Network Diagram
Question2. What is critical path?
Question3. Assume you want to shorten the completion time as much as potential & you have the option of shortening any or all of B, C, D, and G each 1 week. Which would you shorten?
Question4. What is new critical path & earliest completion time?