Network and identify the critical path


Discuss the below:

1. Draw the network and identify the critical path. Also calculate the earliest-latest stav¬ing and finishing times for each activity:

Activity    Preceding Activity    Time (Weeks)
A    —                                   4
B    —                                   6
C    A. B                                7
D    B                                    8
E    B                                    5
F    C                                    5
G    D                                    7
H    D. E                                 8
I    F. G. H                              4

2. On May I. Arnie Watson sent a memo to his boss, the director of project management, stating that the MX project would require thirteen weeks for completion according to the fig¬ure shown below.

957_image.jpgArnie realized that the customer wanted the job completed in less time. After discussions with the functional managers. Arnie developed the table shown below:

Activity        Normal    Crash        Additional (Crash) Cast/Week
    Time    Cast    Time    Cost   
A    3    6,000    2    8,000            2,000
B    5    12.000    4    13,500     1,500
C    5    16.000    3    22,000     3,000
D    4    8.000    2    10,000     1,000
E    2    6.000    1    7.500       1,500
F    3    14,000    1    20,000    3,000
        $62,000

a. According to the contract, there is a penalty payment of 55.000 per week for every week over six. What is the minimum amount of additional funding that Arnie should request?

b. Suppose your answer to part a gives you the same additional minimum cost for both an eight-week and a nine-week project. What factors would you consider before de¬ciding whether to do it in eight or nine weeks?