Net capital assets in the governmental activities


In 2006, the Sim City signed a contract in the amount of $5,000,000 for the construction of a new city hall. Expenditures were $3,000,000 in 2006 and $2,015,000 in 2007, including a change order in the amount of $15,000. What amount should be added to net capital assets in the governmental activities accounts in 2007?

A) $5,000,000

B) $5,015,000

C) $2,015,000

D) None of the above.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Net capital assets in the governmental activities
Reference No:- TGS094847

Expected delivery within 24 Hours