The following is the activity and associated costs for the renovation of the local high school football stadium. The times are in weeks.

Activity

Immediate Predecessor

Time

Cost ($)

A

-

4

25,000

B

-

5

30,000

C

A

3

15,000

D

B

8

50,000

E

B

2

12,000

F

C, D

3

15,000

G

C, D

7

46,000

H

E, F

2

20,000

 1. What is the critical path for this project?

 2. How much of the total budget would be spent in Week 8 (Period 8) with the earliest start budget?