Nash Corporation manufactures and sells custom snowmobiles. From the time an order is placed till the time the snowmobile reaches the customer averages 44 days. This 44 days is spent as follows:
Wait time |
12 days |
Move time |
12 days |
Process time |
5 days |
Queue time |
6 days |
Inspection time |
9 days |
What is Nash's manufacturing cycle efficiency (MCE) for its snowmobiles?