MRP Structure
Consider the bill of material for Product J and the data given in the following table. The gross requirements for J are 200 units in week 6 and 250 units in week 8. Prepare the MRP tables for each item for an 8 week planning period. Use the lot-for-lot lot-sizing rule.
J is dependent on K(1) which is dependent on L(4)
J is dependent of M(2)
Item - Lead time - Quantity on Hand - Scheduled receipts
J 1 0
K 2 20 30 in week 2
L 2 0
M 1 20 10 in week 1
What is the planned orders for J in period 5?
What is the gross requirements for J in period 8?
What are the planned orders for K in period 2?
What are the planned receipts for K i period 7?
What are the planned order for L in period 1?