Problem: In the following MRP planning schedule for item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week.
Item J
|
0
|
1
|
2
|
3
|
4
|
5
|
Gross requirements
|
|
|
75
|
|
50
|
70
|
On-hand
|
|
|
40
|
|
|
|
Net requirements
|
|
|
|
|
|
|
Planned order receipt
|
|
|
|
|
|
|
Planned order release
|
|
|
|
|
|
|