mixed model sequencea production line assembles 2


Mixed model sequence

A production line assembles 2 models of hair dryer: standard (s) and deluxe (D). Each S requires 4 minutes of assembly time and each D 12 minutes. Marketing sells twice as many Ss as Ds.

Prepare a mixed model sequence for the 2 hair dryers. Make it as well balanced as possible.

What is the cycle time, and how many times can it repeat in a 480 minute day?