1. MIRR Project L costs $50,000, its expected cash inflows are $12,000 per year for 8 years, and its WACC is 14%. What is the project's MIRR? Round your answer to two decimal places. Do not round your intermediate calculations. %
2. IRR Project L costs $61,780.78, its expected cash inflows are $14,000 per year for 9 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places. %
3. Project L costs $75,000, its expected cash inflows are $15,000 per year for 10 years, and its WACC is 10%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations.