Minimum cost of crashing the project


Quetsion: What is the minimum cost of crashing the following project by 4 days?







 

Normal

Crash Time

Normal

Crash

Immediate

Activity

Time (days)

(days)

Cost

Cost

Predecessor(s)







A

6

5

$ 900

$1,300

-

B

8

6

300

800

-

C

4

3

500

700

-

D

5

3

900

1,900

A

E

8

5

1,000

1,900

C