Mgt 150- using the 50-50 rule earned value computation what


Project Management Assignment

Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.


Budget

Begun?

Complete?

Actual cost

Earned Value

Task A

3,100

Yes

Yes

3,100


Task B

4,000

Yes

Yes

4,500


Task C

2,500

Yes

Yes

2,250


Task D

4,000

Yes

No

3,500


Task E

3,500

Yes

Yes

4,000


Task F

2,500

No

No

0


1) Using the 50-50 Rule, what is earned value for this project?

2) Using the 0-100 Rule, what is earned value for this project?

3) Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.

4) Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?

5) What is the schedule performance index (SPI)?

6) Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?

7) What is the cost performance index (CPI)?

8) If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).

9) Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also, provide projections for future status.

Solution Preview :

Prepared by a verified Expert
Project Management: Mgt 150- using the 50-50 rule earned value computation what
Reference No:- TGS01726388

Now Priced at $20 (50% Discount)

Recommended (96%)

Rated (4.8/5)