Metal frames for kick scooters are manufactured in two


Metal frames for kick scooters are manufactured in two steps: Stamping and assembly. Each frame is made up of three pieces: one unit of part A and two units of part B.

The parts are fabricated by a single stamping machine that requires a set up time of 90 minutes switching between two part types. Once the machine is set up, the activity time for parts, regardless of type, is 30 seconds each piece. Currently, the stamping machine rotates its production between one batch of 120 part As and 240 part Bs. Completed parts move only when the entire batch is produced.

At assembly, parts are assembled manually to form the finished products. The three parts and a number of small purchased components are required for each unit of final product. Each product requires 30 minutes of labor time to assemble. There are 12 workers in assembly. There is sufficient demand to sell every scooter the system can make.

1) At the current batch sizes, the bottleneck of the system is ________ with a capacity of __________?

Stamping with a capacity of _____________

Assembly with a capacity of _____________

They both have the same capacity with a capacity of _____________

Cannot be determined with a capacity of _____________

2) Which batch size for the stamping machine would minimize inventory and maximize the flow rate for the entire process? Circle the answer below that is closest to the correct answer.